Release an operation (via Gantt diagram)
Only a planned operation (that does not need inventory) and an allocated operation (for which inventory has already been reserved) can be released.
For example: Specific operations can be released for a given production order, while other operations cannot yet be released.
- Choose Production Management in the Navigation Pane.
- Click the element Departments, Machines, (External) Work Centers, Resource Groups or Planning Cells.
-
Do one of the following:
- Choose a department, machine, (external) work center, resource group or planning cell.
- Choose My 'Element'.
- Choose a filter.
- Choose the tab Planning.
-
Do one of the following:
- Select one or more operations, right-click the selected operation in the Gantt diagram and choose Release Operation in the shortcut menu.
- Select a machine or work center in the column Resource, select one or more operations in the sub tab Planning and click Release Operation in the toolbar of the sub tab Planning.
-
If the dialog box Wizard Release Operation appears, choose one of the following options:
- Release all the operations of production order 'NameProductionOrder'
- Release operation 'NameOperation'
- Click Finish.
- Confirm if the dialog box Release Operation appears.