Recalculate OEE Reports

Because some jobs can still be active and provide new OEE information, OEE reports must be recalculated regularly.

OEE reports are recalculated automatically based on the schedule 'Calculate OEE reports' in the Configurator's System Management (by default every 10 minutes). OEE reports can also be recalculated manually upon request.

  1. Select the OEE report of the current shift or of the job of the current shift.
  2. Do one of the following:
    • Right-click the selection and choose Recalculate in the shortcut menu.
    • Click Recalculate OEE Reports in the toolbar.
  3. Confirm in the dialog box Recalculate.