Add a general requirement rule

  • A general requirement rule applies to all planning cells.
  • Only one general requirement rule can be added!
  1. Choose Capacity Management > Rules > Requirement Rules in the Navigation Pane.
  2. Choose the tab General Requirement Rules.
  3. Click New Rule in the toolbar.
  4. Select one or more rule blocks from the option group Possible Rule Blocks.
  5. Click to move the rule blocks to the option group Selected Rule Blocks.
  6. Click Finish.
  7. Edit the name of the rule in the tab General Requirement Rule.
  8. Choose the tab Rule Configuration.
  9. Select a rule block and use the arrows to adjust the sequence.
  10. Configure the rule block, see Configure the requirement rule 'Check over-assignment'.